Updating progress in primavera p65/29/2023 With this, resource actual data has been removed. If you are satisfied with the changes displayed, click on Commit Changes. Primavera will show you the preview of the change. ![]() Select the value as displayed in the snapshot below:Ĭlick on the Change button. Now go back to the Activity window and reset Unit and Cost to zero. “Reset Remaining Duration and Units to Original”įor simplicity, let’s assume that we only have “Labor” resources in this project. “Link Budget and At Completion for not started activities”Ģ. Highlight the project, and checkmark the following 2 options :ġ. To remove actuals, first, go to Project window -> Calculation tab. Now you want to remove actuals so you can develop an “As-Planned” schedule. In this post, I will show you how to do this.Ĭonsider a simple project with actual data as illustrated below: ![]() Assume that you have a Primavera schedule with actual data & progress.